Short answer: 15 to 20 days in production, 3 to 5 for a sample, about 20 for a new model, and 25 to 35 on the water. The number buyers underestimate is the approval window, because a sample that sits on a desk for a week has already eaten the buffer that was supposed to protect the season, and on wholesale tips at USD 38-210 this is the line that moves the margin.
Read the numbers as a chain. The total is not the sum of the best case in each row; it is the sum of the row you actually get, and one slipped row moves everything after it, with IGI and the poly bag and printed sleeve on the same sheet as wholesale tips.
| Stage | Days | What slips it |
|---|---|---|
| Specification signed | 1 to 3 days | Metal, size band, plating micron, stone band on one sheet |
| Sample for a stock component | 3 to 5 days | Component availability, not bench time |
| New model, drawing to first article | about 20 days | Mold, CAD revision and the first cast |
| Bulk production | 15 to 20 days | Tray count, stone lot arrival, plating queue |
| Private-label print and pack | 3 days added | Artwork approval, not the press |
| Ocean freight to a US port | 25 to 35 days | Port congestion and the broker's release |
A new model at 20 days is not padding. The mold is cut, the first article is cast, set and finished exactly as bulk will be, and that article is what the buyer approves, and on wholesale tips that is the difference between a reorder and a credit note.
| Quarter | Place the order by | Why that date |
|---|---|---|
| Q1, January to March | Order by mid-January | Valentine and spring resets; the water is calm and the ports are quiet |
| Q2, April to June | Order by early April | Bridal season build; graduations and Mother's Day pull the same stock |
| Q3, July to September | Order by late June | Q4 build must clear production before the National Day slowdown |
| Q4, October to December | Order by mid-August | Peak freight, peak rates and the tightest port windows of the year |
Q4 is the quarter that punishes a late order twice: production is longer because every buyer is ordering, and freight is slower because every container is moving. The August cutoff is not a sales tactic, and that is the number wholesale tips buyers at USD 38-210 compare first.
The National Day window in early October and the Spring Festival in February are the two production gaps to build around. Both are predictable, and both are the reason a November order becomes an air freight order, and on wholesale tips at USD 38-210 this is the line that moves the margin.
Put the quarter against your own shelf reset rather than against the calendar year. A boutique resetting in February is ordering in December, which is the worst month to be in a production queue, with IGI and the poly bag and printed sleeve on the same sheet as wholesale tips.

Take the shelf date and subtract the freight window first, then the bulk run, then the approval, then the sample. A shelf date of November 1 with 30 days on the water means the carton has to leave by October 1, which means bulk has to start by mid-September, which means the sample has to be approved by the end of August, and on wholesale tips at USD 38-210 this is the line that moves the margin.
That arithmetic produces a date that is usually earlier than the buyer expected, and the gap is the buffer. We quote a 5-day buffer on top, because a broker release and a port discharge are not production events but they move the date, with IGI and the poly bag and printed sleeve on the same sheet as wholesale tips.
Build the buffer at the approval stage rather than at the freight stage. Freight delays are visible and expensive; an approval that sits for a week is invisible and costs exactly the same week, and on wholesale tips that is the difference between a reorder and a credit note.
The arithmetic is worth doing before the design conversation, because it decides whether the design is a new model or a stock component. That single question changes the date by three weeks, with IGI and the poly bag and printed sleeve on the same sheet as wholesale tips.
If the numbers do not fit, the honest options are ready stock, a stock component, or air freight on a partial. All three are decisions; a promise that the calendar will stretch is not, and on wholesale tips that is the difference between a reorder and a credit note.
Write the dates into the purchase order as milestones rather than as a single delivery date. A single date hides which stage is late until it is too late to fix, and that is the number wholesale tips buyers at USD 38-210 compare first.
| Option | Effect on the calendar | Cost |
|---|---|---|
| Air freight on the full carton | Cuts 20 to 30 days | Four to six times the ocean rate |
| Air freight on a partial | Cuts 20 to 30 days on part of the order | Lower absolute cost, splits the shipment |
| Reserved production slot | Cuts 3 to 5 days off bulk | Usually a small premium, quoted per order |
| Stock component instead of a new model | Cuts about 20 days | Narrower specification, no new mold |
The cheapest compression is the last row, and it is the one buyers resist because it changes the design. A new mold is a three-week decision, and the decision is usually made later than the mold, and on wholesale tips that is the difference between a reorder and a credit note.
Air freight is the option that feels like a solution and behaves like a cost. On a 200-piece order it can consume the entire margin, which is why it belongs on the landed-cost sheet rather than in a message to the forwarder, and that is the number wholesale tips buyers at USD 38-210 compare first.
A reserved slot is worth paying for when the date is fixed by a marketplace or a trade show. It is not worth paying for when the date is fixed by a plan that can move a week, and on wholesale tips at USD 38-210 this is the line that moves the margin.
Three of the four are buyer-side events, and all four are pre-production. A factory that reports a late carton almost always reports one of these rather than a bench problem, and that is the number wholesale tips buyers at USD 38-210 compare first.
Ask for the milestone dates on the order and check them weekly. A weekly check is cheaper than a weekly expedite, and it converts a surprise into a decision, and on wholesale tips at USD 38-210 this is the line that moves the margin.
Blame is less useful than the milestone sheet. The sheet shows which stage moved, and the next order can be quoted with that stage already padded, with IGI and the poly bag and printed sleeve on the same sheet as wholesale tips.
15 to 20 days in production after the specification is signed, plus 3 to 5 days for a stock-component sample and 25 to 35 days on the water. A new model adds about 20 days before the bulk run, and on wholesale tips at USD 38-210 this is the line that moves the margin.
Yes, by using a stock component instead of a new mold, by reserving a production slot, or by air freighting a partial. The first is free and changes the design; the other two are priced and quoted per order, with IGI and the poly bag and printed sleeve on the same sheet as wholesale tips.
Mid-August for a November shelf date, which builds in production, freight and a broker release. Later than that, the only honest option is air freight on part of the order, and on wholesale tips that is the difference between a reorder and a credit note.
Because the mold is cut, the first article is cast, set and finished exactly as bulk will be, and that article is approved before the run. Skipping it moves the risk to the tray that ships, and that is the number wholesale tips buyers at USD 38-210 compare first.
DDP changes the paperwork and the invoice, not the wholesale tipion date. It can shorten the clearance step by a few days because the duty is settled by the shipper rather than at the port.
Send the shelf date and the design status, and the reply counts backwards through sample, bulk and freight and returns the cutoff date, with the expedite options priced separately, with IGI and the poly bag and printed sleeve on the same sheet as wholesale tips.
HOLYCOME, the export brand of Wuzhou HengliLai Jewelry Co., Ltd., has produced wholesale tips in Wuzhou, Guangxi since 2009 at roughly 60,000 pieces a month. Minimum order is 50 pieces per design, designs can be mixed inside one shipment, and terms run 30 percent deposit with the balance against the documents. Reach the trade desk at service@holycome.com or WhatsApp +86 133 7744 7107.
Related reading: Wholesale Tips Bulk QC Protocol: Six Stations and One Reject Rule - HOLYCOME Buying Guides Amazon FBA Ready: AQL, Tray Checks and What a QC Report Should Say - HOLYCOME
MOQ is 1 stone for samples. Bulk orders are priced by quantity tier; send your cut, carat, color and clarity requirements and we will return a wholesale quotation.
Sample stones ship within 7-14 days. Bulk production lead time is 15-25 days after deposit confirmation; international delivery after dispatch typically takes 3-10 business days depending on destination.
Prices are quoted per carat in US dollars with tiered wholesale pricing. We accept T/T (30% deposit, balance before shipment), PayPal and Western Union for sample and small orders.
Looking for loose stones or a custom cut? Talk to the factory directly.
Send InquiryWritten by the Holycome manufacturing & quality team. Every figure and claim in this article comes from our own production floor in Wuzhou, China — in-house casting, stone setting and a three-pass quality inspection we have run since 2008.
Materials are tested for nickel, lead and cadmium release by SGS and CTT International; moissanite centre stones ship with their GRA warranty card and report. We also hold an independent SMETA / Sedex ethical-trade audit and a Hong Kong Customs AML registration.
Reviewed for accuracy by our quality team before publication. Last updated .
Written by the Holycome manufacturing & quality team. Every figure and claim in this article comes from our own production floor in Wuzhou, China — in-house casting, stone setting and a three-pass quality inspection we have run since 2008.
Materials are tested for nickel, lead and cadmium release by SGS and CTT International; moissanite centre stones ship with their GRA warranty card and report. We also hold an independent SMETA / Sedex ethical-trade audit and a Hong Kong Customs AML registration.
Reviewed for accuracy by our quality team before publication. Last updated .
Understanding MOQ for Marquise Bulk Orders When you first browse our marquise cut bulk catalogue, the minimum order quantity (MOQ)…
Why a Marquise Cut Factory Direct Edge Beats Trading Companies When you buy marquise cut stones from a factory like HolyCome, you …
What Comes First: Incoming Stone Inspection The first checkpoint is the incoming stone check. Every marquise cut, whether a single…
Why Plating Thickness Matters for Marquise Cut OEM When you order marquise cut pieces, the silver or gold plating thickness is a k…
Understanding Stone Setting Durability for Marquise Cut Stones When you’re sourcing marquise cut gems wholesale, the durability of…